INTERSTATE 81 ACCELERATION RAMP EXTENSION AT EXIT 162 IN BOTETOURT COUNTY – This ramp extension project is underway and as part of the project, the on-ramp from Route 11 onto northbound 81 was previously closed but is now back open. This project will extend the on-ramp onto northbound I-81 about 1,000 feet. The project also includes installing drainage structures and constructing a retaining wall alongside the slope. As work progresses, additional ramp and lane closures may be in place during nighttime hours. During construction, barrier wall will be installed along the right shoulder of northbound I-81 at exit 162. Electronic message boards will alert drivers to the upcoming ramp closure and announce any schedule changes. Work is expected to be completed in late 2026.
LANE CLOSURES:
Weather permitting, alternating northbound and southbound lane closures for drainage improvements will be in place on Route 11 in Buchanan between I-81 and the Exxon station next to the northbound off ramp at exit 162.
Drivers can expect nighttime right and left lane closures in place on I-81. Drivers use caution in the area of the work zone.
INTERSTATE 81 BRIDGE WORK AT EXIT 156 IN BOTETOURT COUNTY – Bridge work is underway on northbound and southbound I-81 at Exit 156. Milling and paving the bridge deck will take place in both directions beginning with the northbound side first and then southbound once northbound is completed. Drivers can expect lane closures on I-81 during nighttime hours. Slow roll operations are expected periodically and flagging operations will be used during barrier wall placement on Route 640 (Brughs Mill Road). Expected completion is fall 2026.
Temporary traffic barrier in place on westbound side of Route 640 under the I-81 bridges off exit 156 with lanes narrowed to 11 feet.
Nighttime outside and inside lane closures may be in place on I-81 from mile marker 155 to 157, 9 p.m. to 6 a.m. the following morning.
INTERSTATE 81 ACCELERATION RAMP EXTENSIONS AT MILE MARKER 94 IN PULASKI COUNTY AND 105 IN MONTGOMERY COUNTY– Work is underway on the extension of two acceleration lanes on I-81. The first one will be the entrance ramp onto I-81 southbound at mile marker 94, the entrance ramp onto I-81 southbound. The second one will be the entrance ramp onto I-81 northbound at mile marker 105 in Montgomery County. Scheduled completion date for both projects is summer 2026. During construction, drivers can expect:
LANE CLOSURES: Nighttime lane closures northbound and southbound from 7 p.m. to 6 a.m., the following morning, Sunday through Thursday.
Shoulder closures throughout the work zone area.
Ramp closures are possible.
Narrowed or shifted ramps during nighttime hours.
INTERSTATE 81 LANE WIDENING CONSTRUCTION PROJECT EXIT 137 TO EXIT 141 – The $179 million design build project to widen both directions of I-81 between mile markers 136.6 and 141.8 from two to three lanes is underway. Work is being performed along a five-mile section of both northbound and southbound Interstate 81 in Roanoke County and the city of Salem. Barrier wall is in place along the shoulders. Two lanes of I-81 traffic in each direction are expected to remain open during the project with periodic lane closures scheduled during nighttime hours or outside of peak travel times as needed. Drivers can expect the following lane closures and upcoming traffic impacts in this area on northbound and southbound I-81:
LANE CLOSURES: Alternating left and right lane and shoulder closures during nighttime hours between 8 p.m. and 6 a.m., Sunday through Thursday, are possible. Lane widths will be reduced to 11 feet. Nightly lane closures may be in place along the right lane with possible nightly ramp narrows as needed for guardrail and shoulder strengthening.
RAMP CLOSURES: Ramp closure of exit 137 and 140 on and off ramps onto southbound I-81 in Salem possible, 12 a.m. to 5 a.m. Watch message boards for updates.
FLAGGING OPERATIONS: Flagging operations possible on Route 635 and Route 619.
UNEVEN PAVEMENT: Drivers may experience some uneven pavement and/or rough surface throughout the project.
TRAFFIC SHIFTS AT I-81 EXIT 140: Drivers may experience periodic lane closures, narrow ramps or quick merges into traffic onto Thompson Memorial Drive from the southbound or northbound exit ramps of exit 140 off of I-81. Work zone located at bottom of the ramp for work on the I-81 bridge at the underpass.
TRAFFIC SHIFTS ON WILDWOOD ROAD: Expect a work zone with traffic shifts and narrow width on Wildwood Road after exiting I-81 southbound on exit 137 heading towards Salem. Southbound and northbound I-81 exit 137 and entrance ramp narrows are possible at Route 311.
WORK ZONE SPEED: Drivers should adhere to posted 60 mph speed limits in the work zone and allow space when following a vehicle. Narrow spacing in lanes due to barrier walls, lack of shoulders and lane shifts in various locations, are present.
The project also includes replacing six bridges, widening two bridges, installing approximately 2.6 miles of sound barrier walls along northbound I-81, improving the southbound exit 137 off-ramp intersection at Wildwood Road and adding interchange lighting at exits 137, 140 and 141. Expected completion in summer 2026.
I-81 WIDENING FROM MILE MARKER 143 TO 150 – The I-81 widening project is underway with survey and preparation work. Shoulder strengthening work will require northbound and southbound lane closures during nighttime hours. Barrier wall installation is possible in late fall or early winter. The expected completion for this project is summer 2031.
PARK AND RIDE AT EXIT 150 IN BOTETOURT COUNTY: Drilling operations with shoulder closures on Route 220 (Roanoke Road) north and southbound. A few parking spaces in the park and ride lot at exit 150 will be barreled off for the drilling operation.
TRAFFIC SHIFT: Southbound traffic is shifted to the right shoulder from exit 150 in Botetourt County to exit 146 in Roanoke County.
LANE CLOSURES: Periodic right and left lane and shoulder closures in place during nighttime hours 9 p.m. to 6 a.m., on northbound and southbound I-81.
RAMPS – Ramps on I-81, northbound and southbound, may be narrowed at exit 150. 146 and 143.
BARRIER WALLS: Drivers will see barrier walls in place throughout the project.
SHOULDER CLOSURES: Shoulder closures in place with additional barrier wall to be installed next year.
WORK ZONE SPEED: Drivers should adhere to posted 60 mph speed limits in the work zone and allow space when following a vehicle. Speed reminders are posted for drivers.
‘PINK’ DETOUR SIGNS: While pink detour signs are in place on I-81 and routes around the project such as Route 11 and Plantation Road, these do not designate a permanent or scheduled detour. The signed detour route is suitable for all traffic during incidents including tractor-trailers and other large vehicles. These signs are used for traffic incident detours only.
I-81 NORTHBOUND AT EXIT 105 NEW RIVER BRIDGE REPLACEMENT IN MONTGOMERY COUNTY – Traffic on northbound I-81 has been switched onto the newly constructed bridge over the New River at the Montgomery/Pulaski County line. Lane and shoulder closures may be in place near exit 105. Lane closure may be in effect during the week from 8 p.m. to 7 a.m. Shoulder closures may be in effect at any time during the week. Slow rolls may be performed on I-81 in the north and southbound lanes from mile marker 98 to 109. Speed limit is reduced to 60 miles per hour in the work zone. Shoulder closures will remain in place though the duration of the project.
LANE CLOSURES: Nighttime right and left lane closures may be in place on I-81 northbound or southbound between mile marker 106 and 104 from 8 p.m. to 6 a.m. the following morning.
ROUTE 605: Alternating lane closures and flagging operations may be present on Route 605, located under the New River Bridge, for paving operations and work overhead on the bridge.
SLOW ROLLS: Slow rolls may be utilized periodically on both the northbound and southbound lanes from mile marker 98-109 for structural steel deliveries and setting beams.
I-81 BRIDGE DECK REPAIRS – Weather permitting, crews will repair bridge decks on Interstate 81 between mile markers 170 to 89, right and left lane closures will be in place northbound and southbound during nighttime hours, 9 p.m. to 6 a.m. the following morning. Drivers should watch for signs and work zone areas. Delays are possible.
INTERSTATE 581 EXIT 2N AT PETERS CREEK ROAD – Work is underway on this $4 million project to re-align and signalize the exit 2N ramp from northbound I-81 to northbound Peters Creek Road, eliminating the current merge ramp and making it easier for drivers to access Valleypointe Parkway. One lane each direction will remain open during work. During spring and summer 2026, the current exit ramp will be narrowed as construction begins on the new exit ramp. Construction is expected to be completed in late fall 2026.
LANE CLOSURES: Drivers can expect intermittent lane closures, 9 a.m. to 2 p.m., on Peters Creek Road northbound and southbound in the city of Roanoke between Valleypointe Parkway and Thirlane Road NW through mid-March.
I-581 PATCHING OPERATIONS – Weather permitting, crews will perform paving and patching operations. Lane closures will be in place northbound and southbound, Sunday through Thursday, during nighttime hours, 7 p.m. to 7 a.m. the following morning. Drivers should watch for signs and expect possible delays.
ROANOKE COUNTY
ROUTE 419 (ELECTRIC ROAD) – Drivers should expect daytime right lane and shoulder closures along northbound Route 419 (Electric Road) for utility work between Cordel Drive and Stoneybrook Drive through March 2026. Delays are possible.
ROUTE 221 (BENT MOUNTAIN ROAD) UTILITY WORK – Drivers should expect daytime flagging along Route 221 (Bent Mountain Road) between Poage Valley Road and Crystal Creek Drive for utility installation through May 2026. Delays are possible.
PETERS CREEK ROAD SIGNAL INSTALLATION – Drivers should expect lane closures along northbound and southbound Peters Creek Road during daytime hours for a signal pole installation and intersection improvements between Dwight Street and South Drive through March 2026.
CRAIG BOTETOURT SCENIC TRAIL BRUSH CUTTING AND STABILIZATION WORK – Residents along the former Chesapeake and Ohio (C&O) Craig Valley Branch railbed in Botetourt and Craig counties may notice maintenance work continuing on the old railbed. These activities are intended to prevent additional deterioration and to help designers who are developing plans for the Craig Botetourt Scenic Trail. VDOT continues to collect data and conduct site visits and field reviews on the railbed. The design plans for Craig Botetourt Scenic Trail are still being refined and a specific schedule for construction has yet to be determined.

