Interstate 81
SLOW ROLLS TO IMPACT I-81 IN ROANOKE – AEP will be performing a slow roll operation for two crossings in both directions over I-81 near mile marker 135.41 and 135.91 on Thursday, September 14 from 12 a.m. to 5 a.m.
I-81 & ROUTE 11 BORING SCHEDULED – Mountain Valley Pipeline is expected to perform boring across Route 11 near Apgar Drive between Sept. 11 and Sept. 26. In addition, boring is tentatively scheduled across I-81 near MM 130.11 between October 26 and November 17.
INTERSTATE 81 LANE WIDENING CONSTRUCTION PROJECT EXIT 137 TO EXIT 141 – A $179 million design-build project to widen both directions of I-81 between mile markers 136.6 and 141.8 from two to three lanes is set to begin. Starting in February and continuing into the early summer, work will be performed on the inside and outside shoulders along a five-mile section of both northbound and southbound Interstate 81 in Roanoke County and the city of Salem. The shoulders will be built up before barrier wall can be installed for road crews to work behind. Barrier wall will be installed along the shoulders in the spring and summer. Two lanes of I-81 traffic in each direction will remain open during the project with periodic lane closures scheduled during nighttime hours or outside of peak travel times as needed. Drivers can expect the following lane closures and upcoming impacts on northbound and southbound I-81:
ADDITIONAL TRAFFIC IMPACTS:
TRAFFIC SHIFT ON WILDWOOD ROAD: Expect a traffic shift with narrow width on Wildwood road after exiting I-81 southbound heading towards Salem. Southbound and northbound I-81 exit and entrance ramp narrows possible at Route 311.
WORK ZONE SPEED: With narrow spacing in lanes due to barrier walls, lack of shoulders and lane shifts in various locations, drivers should adhere to posted 60 mph speed limits in the work zone and allow space when following a vehicle.
RAMP CLOSURES: Ramp closures are possible during nighttime hours, 12 a.m., to 5 a.m. Drivers should watch for message boards dates and times the ramp will be closed.
LANE CLOSURES: Alternating left and right lane and shoulder closures during nighttime hours between 8 p.m. and 6 a.m., Sunday through Thursday, are possible. Lane widths will be reduced to 11 feet. Nightly lane closures may be in place along the right lane with possible nightly ramp narrows as needed for guardrail and shoulder strengthening.
The project also includes replacing six bridges, widening two bridges, installing approximately 2.6 miles of sound barrier walls along northbound I-81, improving the southbound exit 137 off-ramp intersection at Wildwood Road and adding interchange lighting at exits 137, 140 and 141 are also included in the project. Expected completion in early 2026.
I-81 NORTHBOUND AT EXIT 105 NEW RIVER BRIDGE REPLACEMENT IN MONTGOMERY COUNTY – Traffic on northbound I-81 has been switched onto the newly constructed bridge over the New River at the Montgomery/Pulaski County line. The old bridge is being demolished. Lane and shoulder closures may be in place near exit 105. Lane closure may be in effect during the week from 8 p.m. to 7 a.m. Shoulder closures may be in effect at any time during the week. Slow rolls may be performed on I-81 in the north and southbound lanes from mile marker 98 to 109. Speed limit is reduced to 60 miles per hour in the work zone. Shoulder closures will remain in place though the duration of the project. Project completion is estimated by end of year 2023.
SLOW ROLLS: A slow roll operation may be in place daily, Monday through Friday, between mile marker 101 and 105 northbound and between mile marker 109 and 105 southbound, between the hours of 9 a.m. and 3 p.m. Slow rolls may be utilized periodically on both the northbound and southbound lanes from mile marker 98-109 for structural steel deliveries and setting beams.
LANE CLOSURES: Nighttime alternating lane closures will be in place on I-81 northbound between mile markers 104-106 from 7 p.m. to 6 a.m. the following morning.
ROUTE 605: Alternating lane closures and flagging operations will be present on Route 605, located under the New River Bridge, for work overhead on the bridge.
I-81 PAVING OPERATIONS – Weather permitting, crews will be performing paving operations along Interstate 81. Right and left lane closures may be in place along northbound and southbound lanes during nighttime hours, 9 p.m. to 6 a.m. Drivers should watch for moving vehicles and equipment. Expect possible delays.
I-81 BRIDGE DECK REPAIRS – Weather permitting, crews will repair bridge decks on Interstate 81. Between mile markers 170 to 89, right and left lane closures will be in place northbound and southbound during nighttime hours, 9 p.m. to 6 a.m. the following morning. Drivers should watch for signs and expect possible delays.
Interstate 581
I-581/220 EXPRESSWAY PAVING OPERATIONS – Weather permitting, crews will pave, patch and repair pavement on various routes. Lane closures may be in place during nighttime hours, 9 p.m. to 6 a.m. the following morning. Drivers should watch for signs and expect possible delays.
I-581/220 LANE & RAMP CLOSURES FOR PAVING AND MAINTENANCE OPERATIONS IN ROANOKE COUNTY– Weather permitting, crews will be milling and paving along Interstate 81. Right and left lane closures will be in place along northbound and southbound lanes during nighttime hours. Drivers should expect possible delays.
Roanoke City
13th STREET SE IMPROVEMENTS WITH DETOUR – A project to improve a portion of 13th Street SE in Roanoke is nearing completion. Once complete, a new roadway will extend 13th Street to Norfolk Avenue and the intersection at 13th Street and Wise Avenue will be reconfigured to include a roundabout. Bike lanes, sidewalks, crosswalks and curb and gutter will also be added. Southbound 13th Street traffic has a detour in place using Norfolk Avenue onto 12th Street to Tazewell Avenue. Minimal traffic impacts at this time. The project is expected to be completed in late summer 2023.
Roanoke County
STARKEY ROAD AND BUCK MOUNTAIN ROAD ROUNDABOUT – A road project to construct a single-lane roundabout at the intersection of Route 904 (Starkey Road) and Route 679 (Buck Mountain Road) is underway. The new roundabout is now open to traffic and drivers should be aware of the new roundabout configuration. There will be occasional flagging operations in place between the 9 a.m. and 3 p.m. at the intersection of Starkey Road and Buck Mountain Road, drivers should still expect lane closures with flaggers controlling traffic for final paving, additional concrete pouring and pavement marking until the project is finished. Final completion is expected in late spring 2024.
LANE CLOSURES WITH FLAGGING OPERATIONS: Lane closure times of 9 a.m. to 3 p.m. have resumed due to school now being in session.
ROUNDABOUT: The roundabout configuration has been set up. This means drivers should continue around the circle without turning left and that drivers in the circle have the right of way.
FAIRWAY RIDGE ROAD CLOSED FOR PIPE REPAIRS – Beginning on September 11 at 9 a.m. Fairway Ridge Road near the intersection with Franklin Street will be closed for two pipe replacements. Drivers will need to seek alternate routes and message boards will alert drivers in the area. The work is expected to be completed by September 22, weather permitting.
MOUNTAIN VALLEY PIPELINE – Mountain Valley Pipeline is expected to begin full construction again by mid-July. Temporary intermittent flagging operations will be in place in the county throughout the remainder of the project (with a tentative completion date of February 2024) to load/unload equipment at crossings and construction entrances. Scheduled completion is February 2024.
PAVING OPERATIONS – Weather permitting, crews will pave, patch and repair pavement on various routes. Lane closures may be in place and flaggers may control traffic at times during daylight or nighttime hours. Drivers should watch for signs and expect possible delays.
Botetourt County
DALEVILLE INTERSECTION PROJECT FOR FIELDSTONE DEVELOPMENT ACCESS – Lane closures northbound and southbound on Route 220 in Daleville will be in place for construction of a median with crossover, a right turn lane and a new traffic signal. This work is associated with construction of the Fieldstone Development through a permit. Drivers may see the new signal arm and additional signage being added. There is no estimated time for when these will become active as work continues. Lane closures will be set up on various days and noise disturbances may be in place through September 2023.
ROUTE 11 BUCHANAN BRIDGE PROJECT – A construction project on the Route 11 Bridge in the Town of Buchanan is underway. Water Street is closed for the duration of the project. Drivers should expect delays due to a single lane closure across the bridge with a flagging operation. The jacking and bearing replacements have been completed. Contractors are now applying protective paint underneath the bridge and will replace expansion dams on the bridge deck. Message boards are present to alert and update drivers. Expected completion in early fall 2023.
FLAGGING OPERATION – A flagging operation will be in place on the bridge Monday through Friday from 6 a.m. to 6 p.m. through September 2023. Drivers should expect delays.
PAVING OPERATIONS – Weather permitting, crews will pave, patch and repair pavement on various routes. Lane closures may be in place and flaggers may control traffic at times during daylight or nighttime hours. Drivers should watch for signs and expect possible delays.
Craig County
PAVING OPERATIONS – Weather permitting, crews will pave, patch and repair pavement on various routes. Lane closures may be in place and flaggers may control traffic at times during daylight or nighttime hours. Drivers should watch for signs and expect possible delays.
MOUNTAIN VALLEY PIPELINE – Mountain Valley Pipeline is expected to begin full construction again. Temporary intermittent flagging operations will be in place in the county throughout the remainder of the project (with a tentative completion date of February 2024) to load/unload equipment at crossings and construction entrances. Scheduled completion is February 2024.